Tuesday, February 15, 2011

The waiting game


Once you have your architect and contractor all set up it's time to start filing for your permits. Put on your comfy pants, because you're in for a wait. Here is the order of things for our project:

1) Historic Preservation/Division of City Planning (30 Montgomery Street, 14th Floor, Jersey City 07302)
* Timing: 45 day window (this might take a while)

2) JC Municipal Utility Authority (555 Route 440, Jersey City, NJ 07305)
* Timing: 45 day window (turn around usually faster)

3) City of JC Zoning (30 Montgomery Street, 4th Floor, Jersey City 07302)
* Timing: 45 day window (turn around usually faster)

4) Passaic Valley Sewage (30 Montgomery Street, 4th Floor, Jersey City 07302)
* Office Hours: Monday 10-12; Friday 10-12
* Timing: They should review on the spot and sign off. They will let you knowi f additional information is needed on your forms.

5) JC Building Department (30 Montgomery Street, 4th Floor, Jersey City 07302)
* Timing: I don't know yet.